[Testing] Trial-3 Schedule Change
Mary Lou Jepsen
mljatolpc at gmail.com
Wed Aug 8 19:05:46 EDT 2007
I've heard the opposite story - no heroics - just that MP date goal is
still 9/22 from Dandy this week.
I'd hate to not have the software ready due to a misunderstanding. If
the software needs to delay MP - we need to deal with it - but I would
suggest waiting a week before pushing out the software schedule (if it's possible ...)
I will spend the entire week in shanghai next week focused on transition
to MP and get a much better understanding of the levers at play so that
we can make the best collective decisions.
- Mary Lou
On Wed, 2007-08-08 at 16:00 -0400, Kim Quirk wrote:
> Mary Lou,
> After you left the Quanta meeting I pushed Arnold very hard on whether
> there was any way they were going to pull this schedule back in --
> since it is not appropriate to keep changing the schedule with this
> many people involved and he said 'no'. I also checked with Robert and
> Arnold checked with a few people at Quanta. Pushing out is easy,
> pulling in is not.
>
> So, please don't ask for any heroics on Quanta's part. Let's work to
> this schedule and get a good quality build on the laptops for MP.
>
> Thanks,
> Kim
>
>
> On 8/8/07, Mary Lou Jepsen <mljatolpc at gmail.com> wrote:
> If we do this - we do not allow quanta to bring the schedule
> back to
> 9/22 (which is what they are attempting).
>
> If hardware can pull in - can software?
>
> - Mary Lou
>
>
> On Wed, 2007-08-08 at 14:13 -0400, Kim Quirk wrote:
> > Hi,
> > After a schedule discussion with Quanta this morning, we
> have new mass
> > production assembly dates that allow us to adjust the
> schedule for
> > Trial-3 software. Trial-3 is beta-level SW that should have
> no
> > blocking bugs, no regressions from the Trial-2 code, and it
> will
> > include activation, robust upgrades, backup and restore from
> the
> > school server, and a solid (frozen) mesh protocol api. We're
> hoping to
> > get many bug fixes in as well, but not many other features.
> Please see
> > the roadmap for more details:
> ( https://dev.laptop.org/roadmap
> >
> >
> > Here is the new schedule taken right from the roadmap:
> >
> > * Feature Freeze, 8/27/07
> > * Code Freeze, 9/10/07
> > * Release to Quanta, 9/21/07
> > * Final release to Quanta for MP, 9/28/07
> > NOTE: This gives us 2 more weeks (from the original date of
> 8/13) to
> > get to feature freeze for Trial-3. After discussions with
> many groups
> > this week, this time will be well used in order to try and
> meet the
> > goals that are listed in the road map. I still need a more
> detailed
> > schedule for mesh protocol updates (Dafydd is providing),
> activation
> > with crypto, and robust upgrades (from Ivan) to be sure they
> can fit
> > into this new schedule.
> >
> > I'll be away next week so please work with Jim to provide
> updates and
> > progress.
> >
> > Kim
> >
> >
>
>
More information about the Testing
mailing list