[Testing] Trial-3 Schedule Change

Kim Quirk kim at laptop.org
Wed Aug 8 16:00:02 EDT 2007


Mary Lou,
After you left the Quanta meeting I pushed Arnold very hard on whether there
was any way they were going to pull this schedule back in -- since it is not
appropriate to keep changing the schedule with this many people involved and
he said 'no'. I also checked with Robert and Arnold checked with a few
people at Quanta. Pushing out is easy, pulling in is not.

So, please don't ask for any heroics on Quanta's part. Let's work to this
schedule and get a good quality build on the laptops for MP.

Thanks,
Kim


On 8/8/07, Mary Lou Jepsen <mljatolpc at gmail.com> wrote:
>
> If we do this - we do not allow quanta to bring the schedule back to
> 9/22 (which is what they are attempting).
>
> If hardware can pull in - can software?
>
> - Mary Lou
>
>
> On Wed, 2007-08-08 at 14:13 -0400, Kim Quirk wrote:
> > Hi,
> > After a schedule discussion with Quanta this morning, we have new mass
> > production assembly dates that allow us to adjust the schedule for
> > Trial-3 software. Trial-3 is beta-level SW that should have no
> > blocking bugs, no regressions from the Trial-2 code, and it will
> > include activation, robust upgrades, backup and restore from the
> > school server, and a solid (frozen) mesh protocol api. We're hoping to
> > get many bug fixes in as well, but not many other features. Please see
> > the roadmap for more details: ( https://dev.laptop.org/roadmap
> >
> >
> > Here is the new schedule taken right from the roadmap:
> >
> >       * Feature Freeze, 8/27/07
> >       * Code Freeze, 9/10/07
> >       * Release to Quanta, 9/21/07
> >       * Final release to Quanta for MP, 9/28/07
> > NOTE: This gives us 2 more weeks (from the original date of 8/13) to
> > get to feature freeze for Trial-3. After discussions with many groups
> > this week, this time will be well used in order to try and meet the
> > goals that are listed in the road map.  I still need a more detailed
> > schedule for mesh protocol updates (Dafydd is providing), activation
> > with crypto, and robust upgrades (from Ivan) to be sure they can fit
> > into this new schedule.
> >
> > I'll be away next week so please work with Jim to provide updates and
> > progress.
> >
> > Kim
> >
> >
>
>
-------------- next part --------------
An HTML attachment was scrubbed...
URL: http://lists.laptop.org/private/testing/attachments/20070808/bceceab5/attachment.htm 


More information about the Testing mailing list