13.1.0 schedule update
Daniel Drake
dsd at laptop.org
Sun Nov 25 15:17:42 EST 2012
Hi,
Just wanted to point out some recent modifications to the 13.1.0 schedule:
http://wiki.laptop.org/go/13.1.0/Release_plan
We now go into regression-fixes-only mode on December 3rd, and the
final release date is set for January 7th 2013.
So there is a week left for pushing those opportunistic
bugfixes/translation updates in Sugar activities and other components;
from that point onwards we'll clamp down and only ship important
regression fixes.
Thanks
Daniel
More information about the Devel
mailing list