[Testing] 8.2.1 test plan finalized (next: test cases need finalization)
Mel Chua
mel at melchua.com
Tue Dec 9 13:23:15 EST 2008
(The intent of this email is to make "what's going on with 8.2.1
testing" as transparent as possible.)
I checked after the 8am work estimate cutoff, and made sure that the
test plan matched up with the trac tickets listed at [[Eco/8.2.1]] - as
of right now, it does. (Sweet!)
I believe that means that we can consider the list of test cases here as
final (Joe/Kim, please holler if I'm incorrect):
http://wiki.laptop.org/go/Test_cases_8.2.1 (Note that this doesn't mean
the test cases themselves are final - they're very rough! It does,
however, mean that these test cases are the ones that will exist.)
I'll talk with the developers assigned to these 9 tickets and make sure
that we have final test cases (or at least a plan for how to develop
one) before Thursday's test community meeting, and see how close we can
come to getting work estimates for each test case that's finalized.
Help on this would be quite welcome; catch me on IRC (#olpc, freenode,
mchua) if you'd like to pitch in, or email me if you'd like to take over
the job (there's no reason this should be a Mel-specific task).
--Mel
PS: If this email confuses or concerns you, it's my responsibility to
fix that - please send me any questions/complaints that you might have
about this.
More information about the Testing
mailing list