#3942: Rewire / Organize / Doc 1cc Server Room
-------------------------------------+--------------------------------------
Reporter: djbclark | Owner: djbclark
Type: enhancement | Status: new
Priority: normal | Milestone: Opportunity (please help!)
Component: infrastructure-internal | Version:
Keywords: | Verified: 1
-------------------------------------+--------------------------------------
* Lots of things need to be labeled
* Wiring is a disaster - need wire guides etc - network cabling needs to
be redone by professionals.
* Many pieces of equipment with 2 power supplies are both plugged into
the same power strip; there are 2 circuits going into the room; best
practice would be one power supply per circuit, so we are redundant
against both power supply failure and one of the circuits dying.
* Organize cruft. Need cheap plastic shelving.
* Document / label how power works in the room.
== For Doc ==
The room number is 1014. Building Engineering is reachable at
617-491-0709; they have clamp-on amp meters (they take reasings at the
panel which is in the hardware hacking room), but you should ask for them
to bring one when you call. Michael helped me; he was very fast and a
great guy. The original wiring was done by Greg Tucker at 617-512-5262;
any requests of him have a turn arond time of several days.
Circuits 25 and 27 as labeled on the panel go to the server room. As of
now, 27 was at 8.4 amps and 25 was at 2.3 amps. All circuts are 20 amp,
110v.
--